Construction Projects

Current Ongoing Construction Projects within the District:
- Monte Alto Road et al Pipeline Replacement Project: All 8,500 feet of pipe has been pipe-burst along Monte Alto Road. This new pipeline will reduce unaccounted-for water loss and consistent main breaks that have occured throughout Zone 1 over the last 7 years. Work continues from North to South along Monte Alto Road connecting individual residences to the new pipe. 9 out of 51 service connections have been completed. Substantial completion of the project is set to occur by the end of August.
- Zone 1 to Zone 2 Transmission Line Project: Phase II of the Monte Alto Road Project. New installation of a 6,500-foot dedicated transmission line along Avenida Torreon, which will deliver water to two zones, which are currently served by one transmission line. This new pipeline will increase reliability during periods of drought and meet the growing capacity of the District. The project began on June 29, 2026. Over 4,000 feet of new pipe has been installed via HDD (horizontal directional drilling) up to Duende Road. Substantial completion of the project is set to occur by the end of November.
Brief Updates (updated on 7/29/2026):
- Landscaping remediation was scheduled to begin in early July 2026, but has been postponed due to the delayed shipment of meter can components required for installation. Hydroseeding is now scheduled to occur throughout the month of August as the contractor installs new service lines along Monte Alto Road and Bosque Loop.
- The timeline is subject to change as construction continues, but current estimates are that Phase I will be completed in August 2026. Phase II will be completed by November 2026.
Some Common Questions Asked by Residents:
Q: When will the landscape be remediated, including the trenches?
A: Remediation of any disturbances to landscape, as a result of the pipe replacement work, will occur in July once Phase I of the project is complete. To the extent possible, the contractor takes every precaution to ensure that these areas are well marked and/or barricaded during non-construction hours but is unable to completely cover up the trenches until work is complete.
Q: Will I still have access to my driveway or street?
A: Access to the green space, driveways, and surrounding streets is a priority throughout the duration of the project, and every effort is made to maintain normal access whenever it is safe and feasible to do so. However, due to the nature of excavation and underground utility work, there may be periods when temporary restrictions are necessary. These may include partial lane closures, detours, or brief limitations on driveway access while active work is occurring directly in front of a property. Emergency access for first responders is maintained at all times, and efforts are made to accommodate specific resident needs whenever possible.
Q: Why is my pressure fluctuating?
A: Fluctuations in water pressure are often a temporary and expected condition during construction activities within the water system. Changes in pressure can occur as crews adjust valves, isolate sections of the system, or restore service after work. These actions can briefly alter normal flow patterns and pressure levels.
Q: Why does it sound like my pipes are knocking?
A: 'Knocking pipes' typically indicate the presence of trapped air within the plumbing system or sediment buildup inside the pipes. Given the age of the piping in the Monte Alto Rd area, either condition may be contributing to the issue. To address this, it is recommended to release any trapped air before the water reaches the home’s water heater, or to run water within the residence — preferably using a bathtub — for approximately 10 minutes to help flush water.
Q: Why have I lost power, internet, or telephone?
A: Power interruptions can occasionally occur during water line replacement projects due to the proximity of underground utilities. In many areas here in Eldorado, water lines are installed alongside or near electrical infrastructure. For safety reasons, electrical service may be temporarily disconnected to allow crews to perform excavation and replacement work without risk to personnel. The EAWSD conducts underground locating before digging utilizing the 811 NM system but is unable to repair damage to another utility's infrastructure. Services will be restored promptly once the work is completed and it is safe to do so.
We understand the inconvenience this construction work may cause and appreciate your patience as essential infrastructure improvements are carried out.
If there are specific concerns, please call us at (505) 466-1085.
